  • September-October 2015 Compliance/Documentation Audit
  • October 2015 Draft responses
  • November 2015 Draft responses
  • December 2015 First draft of response to all 17 standards due
  • January 2016 Begin the Compliance Certification draft review
  • January-May 2016 Continue revision process
  • April 2016 Submit Compliance Certification and QEP Impact Report to leadership for formal review no later than April 2016 for approval by end of Spring 2016 semester
  • July 2016 Complete final revisions by July 31, 2016
  • September 15 2016 Submit completed Fifth Year Report to SACSCOC on or before 9/15/2016